Dismantling of a galvanizing bath

Dismantling of a galvanizing bath
Year of implementation
2019
Weight of cargo
40 т.
Type of work
Machinery Moving

In 2019, Techno-Mark completed dismantling and loading of a galvanizing bath using Hydraulic Gantry Systems. After an old galvanizing bath had been removed and transported on a trailer, a new galvanizing bath was installed into the pit in reverse order. It took us two working shifts to complete the project.